This week we prepared for our showing of the track at our in house makersfaire on Saturday. The track is fully complete, but we are waiting on the other small scale teams so that we can begin testing. We are right up on our deadline now, so it is a daunting prospect going into our demonstration without any testing beforehand. We will be returning on Thursday and Friday night for testing and adjustment of any problem areas.
This week was the start of the 2nd presentation. The presentations had to be cut short because of the move of the guide way from campus to the 115 Terraine St location. The remainder of the class was spent purchasing our final materials and setting up reimbursements with Tinan. We believe we have everything we need ordered. Also, I found a family friend that can provide access to basic welding equipment! Hopefully it will be enough for us to complete what we need to.